Excerpt | ||
---|---|---|
| ||
MedicineBow Migration Reminder: ARCC Researchers: |
Excerpt | ||
---|---|---|
| ||
HPC Cluster and Data Migrations
|
...
To find more detailed information about these changes, visit |
...
the following page: Upgrade and Expansion 2024 . June 1st, 2024 |
...
: New storage system “Data” |
...
ARCC will being working with users to begin migration from Alcova to “Data.”
...
New HPC cluster “Thunderer” enters beta testing.
go-live. July 1st, 2024 |
...
: New HPC cluster |
...
ARCC will begin working with users to migrate from Beartooth to Alcova, including invested hardware.
...
August 1st, 2024
Alcova data should be migrated to new storage system.
...
December 15th, 2024: All Investment nodes and project data currently hosted on Beartooth must be migrated to the new cluster.
In an effort to make the transition as smooth as possible, we ask that existing projects migrate or request assistance by the following dates:
July 1st, 2024: Data currently hosted on Alcova should be requested and scheduled for migration.
October 1st, 2024: Deadline for projects in Beartooth to begin migration
...
MedicineBow (Working name: Thunderer) go-live. Again, it is important that researchers review important dates and policies. Please review the pages linked above and contact arcc-help@uwyo.edu for any clarification, or with any questions or concerns. |