Excerpt | ||
---|---|---|
| ||
MedicineBow Migration Reminder: ARCC Researchers: |
Excerpt | ||
---|---|---|
| ||
HPC Cluster and Data Migrations
|
...
To find more detailed information about these changes, visit |
...
the following page: Upgrade and Expansion 2024 . |
...
PI request and approval are required for completion of both migrations. Please review https://arccwiki.atlassian.net/wiki/spaces/DOCUMENTAT/pages/2102722579 for a full list of important dates and https://arccwiki.atlassian.net/wiki/spaces/DOCUMENTAT/pages/2099871826 for migration policies that may impact you and effect migration completions. Go-Live dates for Data and Thunderer are as follows. June 1st, 2024: New storage system “Data” |
...
go-live. July 1st, 2024: New HPC cluster |
...
August 1st, 2024: Alcova data should be completely migrated to the new storage system.
December 15th, 2024: All Investment nodes, allocations, and project data currently hosted on Beartooth must be migrated to the new cluster.
To make the transition as smooth as possible, we ask that all existing projects migrate or request assistance by the following dates:
July 1st, 2024: Data currently hosted on Alcova should be requested and scheduled for migration.
October 1st, 2024: Deadline for projects in Beartooth to begin migration
...
MedicineBow (Working name: Thunderer) go-live. Again, it is important that researchers review important dates and policies. Please review the pages linked above and contact arcc-help@uwyo.edu for any clarification, or with any questions or concerns. |