Scheduled Work
This work is tentatively scheduled for completion in two parts and should not impact operations:
February 8th through March 3rd:
Current liquid cooling in the datacenter will be turned off to perform the upgrade and the datacenter will fall back to air cooling during this time.
Liquid cooling is scheduled to be back online by March 3rd.
May 5th through June 15th:
Racks housing Beartooth will have their liquid cooling systems upgraded to increase power load capacity for future node upgrades.
...