Scheduled Work

This work is tentatively scheduled for completion in two parts and should not impact operations:   

  • February 8th through March 3rd:  

    • Current liquid cooling in the datacenter will be turned off to perform the upgrade and the datacenter will fall back to air cooling during this time.   

    • Liquid cooling is scheduled to be back online by March 3rd.    

  • May 5th through June 15th:  

    • Racks housing Beartooth will have their liquid cooling systems upgraded to increase power load capacity for future node upgrades. 

...